GE Power Commissions First-Of-Its-Kind Kashmir Grid Project for Sterlite Power, to Light Up Over Half a Million Homes in Jammu and Kashmir
 

GE Power Commissions First-Of-Its-Kind Kashmir Grid Project for Sterlite Power, to Light Up Over Half a Million Homes in Jammu and Kashmir


Monday، 10 December 2018

  Commissioned two months ahead of schedule, GE’s Grid Solutions substation installation is part of the Northern Region System Strengthening 29 (NRSS29) project, awarded to Sterlite Power by the Government of India

·       The project brings reliable power to citizens in Jammu and Kashmir (J&K) by importing upto 1,000 MW of additional electricity daily from Punjab

·       This project breaks record timing for fastest GIS (Gas Insulated Substation) implementation in India amidst harsh conditions 

New Delhi, India – December 04, 2018 – GE Power’s Grid Solutions business announced the completion of a first-of-its-kind project for a 400/200 kV Gas Insulated Substation (GIS) at Magam village in the Baramulla block of north Kashmir. Part of the Northern Region System Strengthening 29 (NRSS 29) project, this project was awarded to Sterlite Power by the Indian Government through tariff-based competitive bidding in May 2014.  Sterlite Energy recently shared that the commissioning of the project was two months ahead of schedule despite challenging mountainous terrain. The project will provide over half a million Jammu and Kashmir (J&K) citizens access to reliable power sources year-round. The project was led by GE T&D India Limited, the listed entity of GE Power's Grid Solutions business in India. 

The Kashmir valley region in Northern India suffers from blackouts during the harsh winter months – leaving many families exposed to severe cold. The transmission lines spread over 400 km from Samba in Jammu to Amargarh in north Kashmir’s Baramulla district and passes through 11 major towns and districts of J&K.   

GE has commissioned more than four hundred 400kV GIS bays across India, but this project was the first time the company delivered a solution under harsh weather and sub-zero temperatures in India. Situated at an altitude of 1,710 mts (5,610 ft) in the snow-covered hills of Amargarh, this project was implemented in record time amidst tough conditions.  

“Specially designed vehicles were used to transport the heavy equipment from different locations across India and deliver them safely to the site, overcoming several considerable constraints like narrow tunnels and rough terrains,” said Shailesh Mishra, Business Unit Head, Turnkey SolutionsSouth Asia for GE Grid solutions. “Transporting the material through Jawahar Tunnel was especially challenging. For transportation of transformers we had to dismantle the entire lighting rail and fixtures of Jawahar tunnel and re-do it within a limited time window.” Underdeveloped local markets, limited availability of power from the grid and extreme weather conditions all posed significant challenges for the teams. 

“GE is committed to develop and improve India’s electrical infrastructure to ensure that the citizens have access to consistent and reliable power year-round, no matter what the weather conditions are. Our partnership with Sterlite Energy is just the next step in meeting the growing energy demand of the country,” said Sunil Wadhwa, Managing Director, GE T&D India Limited and Leader of GE’s Grid Solutions business in South Asia. “Every team member that was involved in this project should be incredibly proud of what we have achieved – delivering a critical solution, under severe conditions and in record time.”

 

“Sterlite Power is committed to empowering humanity by addressing the toughest challenges of energy delivery. NRSS-29 project is testament of the same. This is one of the largest private sector transmission projects awarded in the country and is critical for meeting the power requirements of the state,” said Ved Mani Tiwari, CEO, Sterlite Power. “This is especially true in Kashmir, which suffers massive load-shedding during winters when electricity demand rises sharply. The GE team has done a phenomenal job in achieving this feat, particularly given the tight project timeline and rough, mountainous terrain.”

Source : Link

Pasargad Energy Development Co. (PEDC) is an independent energy company based in Iran. PEDC is an integrated energy company whose activities span the entire value chain including exploration, production, refining, petrochemicals marketing, power generation & renewables as well as new high-tech venture capitalizing. Our headquarter is located in Tehran. PEDC is present across the Iranian continental shelf and international market through its subsidiaries. We create value for our shareholders through active investment, high-level monitoring of our projects, building world-class partnership and managing our risks effectively and making balanced portfolio. Meantime, we contribute to the sustainable development of the energy sector and communities in our country. PEDC’s competitiveness relies upon our values-based performance culture, with a strong commitment to transparency, cooperation and continuous operational improvement. As a wholly owned subsidiary of the Pasargad Financial Group, with Pasargad Bank being a distinctive shareholder, we owe our success to our experience, management knowledge and strong local/international partnerships since 2008. PEDC is committed to maintaining sustainability and being recognized as the strategic partner of choice in Iran’s energy and petrochemical sector.​